It takes 3600 person hours to complete a project. How many weeks will it take a team of 15 people to complete the job if each person works 8 hours, 5 days a week

Respuesta :

Answer:

6 weeks

Step-by-step explanation:

x = # of weeks

15 times 8 times 5 = 1 week,

so 15 times 8 times 5 times x = 3600 is the equation

Solve for x to get x = 6